Inspection Piping system

Back to overview

WHAT

Inspecting the wall thickness of a pipe at a steel factory.

Period
November 2018

Client
Bilfinger Industrial Services

WHERE

At a steel factory in the Netherlands.

 

WORK ACTIVITIES

Our client wanted to know the status of the pipeline. By using ultrasonic testing, the thickness of the pipeline can be charted. We carried out this wall thickness test with a team of 4 technicians in 2 days. After the work we provided the client with an extensive report.

 

WHY ROPE ACCESS?

These activities were carried out during a 3-day ‘stop’. Because of this short lead time there was no other possibility to carry out the work than using rope access.

Similar projects

Always on top

Sign up for our updates.

Rope acces energie